Bioenergy Suceava SRL

The City of 100.000 Suceava in the North-East of Romania has a district heating system, which is being supplied from a coal-fired power station. As compensation for the outdated coal-fired power station URBAS established as general contractor a modern Biomass Power Plant of impressive dimensions. Among the power plant technology URBAS also established an extensive combustible processing and transport system as well as the whole power plant infrastructure.

COUNTRY: Romania
PERFORMANCE: 4 x 30 to/h • 31 MWel
PRESSURE: 78 bar
TEMPERATURE: 540 °C
EXTRACTION: max. 71.000 kW
+ 15,000 kW hot water boiler
+ 3 x 15,000 kW gas boilers